ARC Towson Bridge


ARC’s Towson Bridge Project was a project which required hundred of hours of planning months in advance to complete the job in less than 36 hours. ARC had been selected by the client to perform this work because of the outstanding performance record for other projects at the property. ARC’s record gave the owner the confidence that ARC could get this work done in a timely, efficient, and most of all safe manner.

The Towson Bridge project was the removal of a pedestrian bridge spanning Fairmount Avenue in Towson MD. The Bridge went from the Sheraton Hotel on the east side of Fairmount Ave. to Towson Town Center on the west side of Fairmount Ave. For months the Bridge had been closed to pedestrian traffic because of the deteriorating conditions of its support columns. The owners of the bridge had decided it was time to remove it completely and remove and public safety hazard which may exist due to the poor condition. The owners left it up to ARC to determine the best means and methods for getting this done.

Several constraints were placed on ARC to do this project:

  • Fairmount Avenue is a major thoroughfare in Towson and shut down of the roadway had to minimize the impact to traffic patterns as much as possible.
  • Once start, the bridge demolition could not stop without putting the public at risk.
  • The road way beneath the bridge needed to remain intact.
  • The Sheraton across the street and the mall would both remain open and active throughout the bridge removal process.

These constraints led ARC to the following plan of action.

  • The bridge removal work would need to be done on the weekends so as to mitigate the impact to business traffic.
  • The bridge would need to be completely removed at one time so as to prevent any public risk of people driving under a partially demolished bridge.
  • The bridge would need to be dissembled via the use of two 400 ton cranes, the same way it was put together, so as to prevent damage to the adjacent buildings and roadway.

The final result of all the planning and effort was that on a Friday night in August, ARC, and a team of 5 other contractors and over 50 workers mobilized to begin dissemble of the bridge. Less than 36 hours later, a full 21 hours ahead of schedule, the bridge and support columns would be gone, the road way swept, the ground top soiled and strawed, and it would appear as though a bridge was never there. Superior planning and coordination made this an extremely successfully project.

Share this project:
Facebook
Twitter
LinkedIn

What ARC means to the people we serve...

Featured News & Insights

Warehouse

Talking to vendors: Quick tips for getting it right

Be Informed- The more information the better. Knowing where a company stands and the details about the product/ service being offered is crucial. Straight to the point- Cut out jargon and be polite and honest. Ask Questions- Always ask questions.

Moldy bathroom wall

Mold in the commercial and residential setting

Let’s be honest, mold is scary. Whether it is in your home or in your work space, it is crucial to hire a company that understands the impact mold can have in these spaces and even more important to hire

Classroom

Training Up-keep

In this discussion we will cover the importance of training and its up-keep within a company setting. We will discuss the basics, the training matrix, and the issues that come along with keeping everything up to date and in order

Worker wearing protection

5 Things To Remember for New Silica Dust Regulations

OSHA has issued a final rule to limit workers’ exposure to respirable crystalline silica (March 2016, OSHA Respirable Crystalline Silica in Construction Regulation – 29 CFR 1926.1153), a common construction material (e.g., concrete, brick, mortar, granite, sand). Scientists have long